Before the groundworks began I hadn't really taken in the complexity
of the new drainage, rainwater harvesting and soakaways. In fact that's
been far more complicated and taken far more time than digging the
foundations. Access around the bungalow is very limited and once the
groundworkers have put a drain in somewhere they can't drive back over
it with the digger for risk of crushing it. I've been impressed
repeatedly by the skill of the groundworkers and how well they've
planned the work so they can get to it all and then escape from the
site. I briefly considered attempting all the digging myself but I'm so
glad I didn't. It would have been a right mess.
There's
one set of drains to channel rainwater to the tank from the tiled
(relatively clean) parts of the roof. Another set of drains take
rainwater from the green roof to a soakaway, avoiding the harvester
tank. Then there's the soakaway and the harvester tank themselves.
Finally there's the new foul drains (sewers) from the toilet in the
extension and new drain from the existing bathroom, now linked up to the old sewer. A lot of new pipework! But it should all help to make the bungalow fit for the next 40 years and beyond.
All the foundations are now dug, hooray! I'm so happy to
have the extension foundations dug at last (and to have some hardcore
down under it, the lagoon of mud is no more). The new-build strawbale
extension feels in some ways like the main part of the project, though
in reality it's probably the most straightforward part (ugrading the
existing bungalow is much more complicated). Straightforward but
blooming hard work, below ground at least. I've spent most of this week
shovelling gravel and going over layers of it repeatedly with a
compacter plate (Wacker machine), following the same design of
cement-free foundations as for the wrap and the conservatory (see
last blog post) only on a much bigger scale.
The
structural engineer and building inspector have insisted on 1 metre
deep foundations because of the clay it's built into, and the wide bale
walls mean wide foundations (70cm wide). When it was dug out it was
basically a moat, rendering the extension area inaccessible. So far 17
tonnes of stone have gone into the those foundations. I had help from
one of my sisters and my brother-in-law who wonderfully re-arranged some
of their week so they could help me. After seeing the scale of it
Caroline came back for a bit the next day too. I think with their help
we got about 8 tonnes in (it comes in 1 tonne bags), leaving 9 tonnes
which I seem to have shovelled in on my own. I'm stiff and I ache an
awful lot but I seem to have got away with it.
I've mostly managed not to look at the whole amount to do with the gravel
and just to plug away at it. A certain amount of delirious hysteria
has definitely crept in though. I hope my future neighbours aren't
bothered by me talking and laughing to myself as I stumble in and out of
the moat with a shovel, a rake or the magic beepy stick (laser site
level).
Another - hopefully final - 10 tonnes of gravel are now onsite
(at least, they should have arrived this evening, I haven't been up to
check) hopefully to go straight in the foundations first thing tomorrow,
this time with help from the builders. I've caved in and called them
back to help because the bales arrive tomorrow too. The only place the
bales can go is in the level area that will be the extension, and they
can't go there until the gravel isn't in the way. The gravel can't be
stored anywhere else either: the only other possible space needs to be
clear for a new water pipe to be dug through it on Saturday.
I'm
not ready for the bales, they're going to be in the way, but
understandably the farmer who produces the dense, regularly-sized
construction bales needs his barn-space back. The phone call saying he
was sending them on Friday, essentially whether I'm ready or not, tipped
the balance of calmness well towards the manic. I feel like a
green-build Quasimodo, hunchbacked from all that gravel, stumbling
around exclaiming "The bales! The bales!".
During the week I read
this blog about strawbale selfbuild by Andrew Morrison (
www.strawbale.com/staying-sane-during-your-build/).
I seems like sound advice and I was pleased to find I was already
following most of it. Number 1 is "expect the stress". Wise words.
|
Hole for rainwater soakaway. Water from the tiled roof will collect in the rainwater harvesting tank, but still needs somewhere to overflow if there's a storm and the tank is already full. More lovely clay stored up now from this hole. |
|
The soakaway crates. Simple way create a void that can fill with excess water before it soaks away, without recourse to huge amounts of reinforced concrete. It's wrapped in geotextile to prevent ingress of roots and soil. Although it looks like just glorified milk crates, apparently you can drive 20 tonnes over it once it's buried. |
|
Lowering it into the ground with the digger. I had a brief funny moment here, when excitement at getting it done mixed with odd feelings about the grave/coffin-like nature of the whole thing. |
|
Anna watching, with support from apple tree |
|
100mm of pea gravel on all sides. Cleared area is where inlet pipe now sits. The inlet flows from a leaf collector after the harvester tank (which sort of spits out any leaves that get in to the filter at the top of it). The rainwater from the green roof will join the drain at the leaf collector and flow straight to the soakaway (chance of fine soil particles in it - would clog harvester tank over time) |
|
Covered back over with the turf so carefully removed by the groundworks guys. very neat job. |
|
A rare dry moment in the mud. Running through this area now are two sets of drains (one for the harvester tank, one straight to soakaway) and the tank itself. |
|
Fully functioning plumbing. The loo is belatedly joined by the sink in their new location (though probably not the loo and sink we'll ultimately use). I find (successful) plumbing very satisfying. |
|
Couple of small test holes to judge level to reduce-dig to for the extension. Filled with rainwater of course. |
|
Foamglas (cellular, airated insulating block made from mostly recycled glass). Very high comressive strength too. Will form the inner wall of the foundation plinth that the bales will sit on, making the foundations themselves insulating to cut down on heat loss through the floor and foundations. |
|
Ready for setting out string-lines for brickwork. Or for vampire attack. |
|
Natural Hydraulic Lime (NHL) for building the foundation plinth walls with (mixed 1:3 with sand to make mortar) |
|
Bricks and sand too. Might actually get to do some building soon! |
|
Making the most of the quality clay we finally found in the tank and soakaway pits to make some rough clay plaster tests. Aim is to gauge roughly what proportion of sand and clay will produce strong plaster without too much cracking. In reality the plaster will be made up with finely chopped straw too. |
|
Reduce dig for the extension, removing the mush and finding harder ground |
|
Replacing mush with hardcore |
|
Blue line marks the outside of the foundation trench |
|
1metre deep, 700mm wide. Pink area in left side of trench = where the manhole for the old foul drain was dug out and back-filled |
|
New drain for the toilet in the extension and the sink in Anna's studio. Connects with the new drain from the bungalow in the black inspection pit. |
|
Grey-line to the right is another new rainwater drain, which will collect run-off from the green roof. |
|
Lovely straight-sided trenches messed up by the concrete strip foundations for the old garage sticking a few inches into them - so had to be taken out, hence big holes on left. |
|
Add caption |
|
So that's where the rainwater's been going: small soakaway made from rubble at the base of the downpipe. Considering these little soakaways appear to have worked fine, our ridiculously oversized one certainly ought to do the job. |
|
This was once the front lawn. Nearer pile of more-yellow earth is another store of lovely clay for plaster. The rest is the rubbish from most of the extension footings. Towards the back of the bungalow the ground is all mixed up rubbish, made-up ground from when they built the bungalows. Towards the front the clay is nearer the surface as it follows the original sloping ground level. |
|
Final foundation trench finished! Clay just below the surface here. The existing bungalow foundation were clearly just dug into the top of the clay only. They step down towards the back as the clay goes down the hill. |
|
Supports for rain-cover |
|
Covered to try and prevent them filling with rain before I can fill them with compacted gravel |
|
Earth-pile neatened up a bit and sealed while it awaits removal. |
|
Open to the morning sun the next day |
|
Add caption |
|
I used to do paintings that looked a bit like this. At least, this is how they looked in my mind. |
|
The dark line is the original ground level from before the bungalows were built, sloping off downhill to the left. |
|
Giant trench lined with geotextile and ready for gravel to go in, as before compacted in layers of 100 to 150mm |
|
Much time this week spent with just me, a shovel, a wheelbarrow, and a whole heap o' gravel. I had help for about 8 tonnes of it, leaving 9 that I apparently shovelled in and compacted alone. |
|
The dog inspects the foundations |
|
The far side of this trench started to collapse from the weight of the forklift pushing down on it after Mark the builder fork-lifted the bags of stone into the middle for me, so I had to get it filled quickly before it could cave in. |
|
Underneath the covers. It takes about half an hour at each end of the day to uncover and re-cover the trenches for the extension; trying to keep them dry and safe from rain-induced collapse until they are full |
|
17 tonnes of "40mm clean" gravel, and still the darned trenches aren't full. Another 10 coming tomorrow. I've given in and asked the builders for help so we can get it in asap. Apart from anything else we need it out the way so there's room for bales when they arrive! |